Mình có một số câu mà không đủ kiến thức trả lời, ace nào giúp hướng dẫn giải đáp giúp mình lý do chọn câu đúng. Cảm ơn!
1. Which of the following statements about the component testing standard is false:
- A black box design techniques all have an associated measurement technique
B white box design techniques all have an associated measurement technique
C cyclomatic complexity is not a test measurement technique
D black box measurement techniques all have an associated test design technique
E white box measurement techniques all have an associated test design technique
- A The use of a variable before it has been defined
B Unreachable (“dead”) code
C Whether the value stored in a variable is correct
D The re-definition of a variable before it has been used
E Array bound violations
- A Test items (i.e. software versions)
B What is not to be tested
C Test environments
D Quality plans
E Schedules and deadlines
- A ISO/IEC 12207
B BS7925-1
C BS7925-2
D ANSI/IEEE 829
E ANSI/IEEE 729
- A all the planned tests have been run
B time has run out
C all faults have been fixed correctly
D both a) and c)
E it depends on the risks for the system being tested
- A code reviews
B code inspections
C a coverage tool
D a test management tool
E a static analysis tool
- A report on deviations from the project plan
B sign the system off for release
C re-allocate resource to meet original plans
D raise incidents on faults that they have found
E provide information for risk analysis and quality improvement
- A black box design techniques all have an associated measurement technique
B white box design techniques all have an associated measurement technique
C cyclomatic complexity is not a test measurement technique
D black box measurement techniques all have an associated test design technique
E white box measurement techniques all have an associated test design technique
- A No, because they apply to development documentation
B No, because they are normally applied before testing
C No, because they do not apply to the test documentation
D Yes, because both help detect faults and improve quality
E Yes, because testing includes all non-constructive activities
- 1. led by author
2. undocumented
3. no management participation
4. led by a trained moderator or leader
5. uses entry exit criteria
s) inspection
t) peer review
u) informal review
v) walkthrough
- A s = 4, t = 3, u = 2 and 5, v = 1
B s = 4 and 5, t = 3, u = 2, v = 1
C s = 1 and 5, t = 3, u = 2, v = 4
D s = 5, t = 4, u = 3, v = 1 and 2
E s = 4 and 5, t = 1, u = 2, v = 3